Page 59 - 건축구조 Vol. 29 / No. 04
P. 59

The Londoner hotel   Project focus  Project focus   The Londoner hotel

                                                                                Digging deep: design and construction of The Londoner hotel

 forces in them under vertical loads, even when   load. The two cases are considered separately   Six trusses were utilised in total, each   FIGURE 11: Aerial view of basement excavation  spoil every day. The removal of earth was an

 considering a balanced arrangement such that   as per the Building Regulations. The upward   weighing over 60t.  amazingly effi cient operation, with an 18t lorry
 the support node was at the neutral axis. This   vertical load case was demonstrated to not   leaving site every four minutes.
 issue was resolved by releasing the trusses   exceed the vertical load from the building above   Construction methodology  Technology played a huge part in enabling
 laterally at one end on directional bearings   and therefore does not govern the design.   Top-down versus bottom-up  McGee to carry out this exercise so effi  ciently:
 (Figure 9), with propping provided by additional   For the horizontal case, it was shown that the   When constructing a deep basement, there are   |  A bespoke vehicle inspection app was

 steels that can be seen adjacent to the truss in   truss members had suffi cient capacity, but this   two primary construction methods: top-down   developed to ensure the  eet of lorries was
 Figure 10.  scenario also applied a horizontal load into   and bottom-up. The construction method and   fully operational.
 The building was classed as Consequence   the truss support bearings, which had to be   sequence are fundamental to the design of the   |  The Locatu manager  was used to optimise
                                                                                                2
 Class 2b as per Building Regulations Approved   designed to resist this force.  basement and must be considered upfront.  the routing of vehicles, in combination with
 Document A. However, the trusses are   In addition to the horizontal forces from   Top-down construction involves installing   cameras located around the site to  ag any
 considered to be key elements and are capable   a blast load case, the bearings had to be   piles and plunge columns from ground level to   potential vehicles blocking the route, allowing
 of sustaining an accidental design loading   designed to accommodate the maximum range   basement-formation level, before casting the   issues to be resolved quickly and minimise
 of 34kN/m  applied to the member and any   of movement, along the axis of the trusses, that   ground- oor slab. The ground- oor slab is then   congestion around the site.
 2
 attached components. This design load is   could be experienced in a  re scenario due to   undermined, excavating to the next basement   |  Weight loading indicators on the vehicles
 assumed to act simultaneously with the other   thermal expansion. This movement is on top   slab level, and the  rst basement level is cast.   highlighted when the maximum 18t limit was
 design loads on the building, but using an   of the horizontal de ection experienced due to   The process of excavation and construction of   reached.
 accidental design combination of actions.  movement of the retaining wall. As such, the    oors slabs is repeated until formation level is   |  A bespoke mobile dashboard was developed
 In the case of a blast above the ballroom, this   bearings allow for 280mm of positive movement   reached.  to allow everyone in the site team to see
 applies a downward pressure in addition to the   and up to 60mm of negative contraction.   One of the major advantages of top-down   information regarding progress.
 vertical load of the building above the trusses.   The bearings, weighing nearly 3t each, and   construction is that work on the superstructure
 This was shown to not exceed the ULS design   the supporting capping beam and reinforced   can occur simultaneously to construction of   In total, over 8000 lorryloads of earth were
 case for the trusses and did not govern the   concrete corbels at either end were designed   the basement, providing scope for programme   removed from site during the excavation. A
 design.  to carry the loads of the trusses at the most   savings. This method also negates the need for   long-reach hydraulic excavator was developed
 A blast within the ballroom could generate   onerous position. The bearings were also   a temporary propping system, as permanent   speci cally for the project. Whereas projects
 both a horizontal and vertical upward blast   designed for maintenance and replacement.  prop slabs are installed as the dig progresses,   traditionally have a topping-out ceremony when
 also helping to minimise ground movements.                                    the tallest point of the structure is reached, we
 However, these bene ts usually come at                                       celebrated with a bottoming-out ceremony, with
 FIGURE 9: Articulation of steel truss  an increased cost of construction. Another   news crews present and a time capsule buried
 drawback of this method is that the vertical                                  35m below the ground.
 tolerance of plunge columns can lead to   loading could have been supported on the   concrete encasement required in the permanent
 large column areas on the lower  oors of the   plunge columns. This would have limited   case, meant the columns would have needed to   Piling
 basement.  the  nishes and  t-out that could have been   be larger than with a bottom-up arrangement,   Once the formation level of the basement
 Bottom-up construction, on the other hand,   achieved on the superstructure  oors before   even if high-strength steel was used, taking up   was reached, the process of constructing the
 involves a phased sequence of excavation   this milestone.  valuable space within the basement.  building could begin with piling for the raft slab.
 and installation of temporary props as the dig   These considerations led to the decision to   This presented its own challenges.
 progresses to the full basement depth. This   These two constraints limited the programme   adopt a bottom-up construction approach.  A piling rig was lowered into the excavation.
 allows access to construct the foundations   advantages that can typically be achieved with   Due to the temporary steel props restraining the
 before installing permanent prop slabs, working   top-down construction. In addition, tolerances   Basement excavation  basement walls (Figure 11), height and access
 from the bottom up. It also allows the dig to   on the plunge column verticality, estimated   In order to create the basement, 75 000m    to the corners of the basement was limited.
                                                                         3
 progress faster than in the top-down method;   to be in the order of ±100mm at the base of   of London clay was excavated prior to   To ensure the piles in these locations could be
 however, work on the superstructure cannot   the excavation, together with the reinforced   construction, with up to 150 lorries removing   installed, the pile cages were delivered to site in
 start until after the basement dig is complete.                               sections which could be joined over the bore.
 The positioning of the temporary props also                                     A smaller piling rig was utilised that could
 FIGURE 10:   needs to be carefully coordinated to ensure the                 operate under the temporary props, and the pile
 Installation of
 steel truss  basement can be constructed around them.                         locations had been carefully coordinated so that
 The choice between bottom-up and                                              cages could be threaded between the props.
 top-down basement construction was not a
 straightforward decision on this project. Initially,                          Truss fabrication and installation
 the contractors, who the design team engaged                                  The transfer trusses were formed from UC
 with, preferred a top-down approach. However,                                 sections up to the maximum 356 × 406 × 1299
 later assessment found this option to be less                                 UC. It would have been diffi cult to splice the

 favourable for two main reasons:                                              trusses together on site with a bolted solution.
 1)  Multiple transfer structures within the building                          Welding sections would have also been a

 mean that load is concentrated in a handful                                   diffi cult and lengthy site operation. The trusses
 of the columns in the basement. For a top-                                    were therefore fabricated off  site with full-
 down approach, the team explored using                                        penetration butt welds (FPBWs) formed at the
 2.4m diameter piles under these heavily                                       connections (Figure 12).
 loaded columns. However, these piles were                                       It is critical that welding steel of this type
 unable to support the large loads, meaning                                    (HISTAR 460) and thickness (up to 140mm
 additional temporary plunge columns would                                     thick) is carefully considered and managed, with
 have been needed to support the transfer                                      speci c welding procedures developed.
 structures at intermediate points before the                                    Initially, there were some concerns about
 raft slab was cast. Furthermore, the piles                                    the weldability of HISTAR steel due to pre-
 would have penetrated the Lambeth group                                       existing data, in particular results of low fracture
 and Thanet sands, requiring bentonite plant   FIGURE 12:                     toughness in the fusion line and heat-aff ected
 to stabilise them during construction.  Truss weld –                          zone of the weld area.

 2)  Before the raft slab was cast and plunge   through ange of                 As a result, the fabricator, Allerton Steel,
          chord member
 columns encased in concrete, only temporary                                   produced pre-welding procedure speci cations
 31                                                         32
 thestructuralengineer.org  |  July 2022          July 2022  |  thestructuralengineer.org  Journal of  The Korea  Structural  Engineers Association  57
                                                                한국건축구조기술사회지

 Londoner Hotel_TSE July 2022_The Structural Engineer.indd   31  22/06/2022   17:56  Londoner Hotel_TSE July 2022_The Structural Engineer.indd   32  22/06/2022   17:57
   54   55   56   57   58   59   60   61   62   63   64