Page 56 - 건축구조 Vol. 29 / No. 04
P. 56

The Londoner hotel   Project focus            Project focus   The Londoner hotel

                해외작품소개

                                                  FIGURE 5: Diagrammatic cross-section of building  slab, a drainage layer was provided to stop   FIGURE 7: Prop slab load path                           river terrace deposits, with contiguous piles
                Box 1. Overview of basement                                           high water pressures developing beneath the                                                                           for the remaining depth. The male piles were
                design                                                                slab. A decision was made not to provide                                                                              1180mm diameter and spanned between the
                                                                                      a heave void, as this would have increased                                                                            prop slabs resisting the earth pressures. In front
                |  Pile wall to basement perimeter: secant                           ground movements around the excavation. The                                                                           of this sits a nominal 425mm thick reinforced
                  to 8m depth to provide water cut-off in                              foundations were therefore designed to resist                                                                         concrete liner wall designed to resist hydrostatic

                  river terrace deposits, with contiguous                             the large heave pressures.                                                                                            pressures.
                  piles for the remaining depth; male piles                            In principle, a raft alone could have provided                                                                         Tolerance on the piles was a key issue, as

                  1180mm diameter.                                                    suffi cient foundation capacity, but the uneven                                                                         any lack of verticality had the potential to eat
                |  Nominal 425mm thick reinforced                                    distribution of load meant that piles were                                                                            into the 425mm liner wall and reduce the size
                  concrete liner wall, doweled to pile wall                           needed to control movements and deal with                                                                             of the basement. For a basement of this depth,
                  to resist lateral earth and hydrostatic                             areas of uplift due to heave. A piled raft analysis                                                                   this was fundamental, e.g. a 1:100 verticality
                  pressures.                                                          was carried out, modelling the relative stiff ness                                                                     tolerance could result in an approx. 600mm
                |  Capping beam to top of pile wall,                                 of the soil and piles and various loading                                                                             reduction in basement size. To control tolerance,
                  varying in depth from 1.6m to 3.1m to                               scenarios.                                                                                                            a guide wall was used and the piles were cased
                  suit change in level across site.                                    Heave pressures increase over time, so the                                                                           for the  rst 15m. An allowable tolerance of
                |  1500mm thick piled raft to bottom of                              maximum settlement and pile loads occur when                                                                          1:200 was speci ed for the cased section and
                  basement, with local pits for lifts and                             the building is  rst complete, in combination                                                                        1:75 for the uncased. The speci ed tolerances
                  drainage tanks. Raft and piles were                                 with a full suite of imposed loads. However,                                                                          were generally met across the site.
                  designed to resist heave pressures but                              when the maximum heave pressure is applied in                                                                           A reinforced concrete capping beam is
                  not hydrostatic pressure, as underside                              combination with minimum vertical loads, piles                                                                        provided around the head of the piled wall
                  was drained.                                                        can go into tension with upwards de ection                                                                           along the perimeter of the site. The capping
                |  Four levels of 350mm thick reinforced                             exhibited. These are at a maximum to the north                                                                        beam is stepped in three locations to suit the
                  concrete prop slabs, plus one partial   FIGURE 6: Cross-section through building showing   of the site where columns are carrying a lower   FIGURE 8: Non-prop slab connection details  changing ground levels and the geometry of the

                  prop slab, to transfer lateral earth   different ground conditions   axial load due to transfer structures at the upper                                                                    connection to ground- oor slabs and transfer
                  pressures across basement void.                                     levels.                                                                                                               trusses.
                |  Six S460 HISTAR transfer trusses,
                  spanning up to 21m and weighing over                                Prop slabs                                                                                                            Transfer structures
                  60t each.                                                           As well as supporting vertical loads, the basement                                                                    On the bedroom  oors, columns were provided
                |  Four levels of temporary steel props,                              oor slabs resist signi cant lateral earth pressures.                                                               at regular centres hidden within partition walls,
                  specially fabricated for the project.                               A coarse 3D  nite element (FE) model of the                                                                          allowing shallow reinforced concrete  oor slabs
                                                                                      basement with each of the prop slabs was created                                                                      to be used. However, below the bedroom levels,
                                                                                      in Oasys GSA  to understand how the lateral                                                                           several column-free spaces were required to
                                                                                               1
                Groundwater observations indicated water to                           loads were transferred between levels through                                                                         allow for open-plan function and reception
              have been encountered at between 4m and 6m                              the basement perimeter walls and stability                                                                            spaces. The arrangement led to various transfer
              depth. This suggested a potential for a shallow                         cores. The model was staged to capture the                                                                            structures throughout the building, the majority
              aquifer to be present within the river terrace                          behaviour of the basement as each  oor was                                                                           of which are located at ground and  rst  oor.
              gravel perched on top of the London clay. The                           installed and the subsequent temporary props                                                                          Incredibly, the building contains only two
              Lambeth group and Thanet sands beneath                                  were removed, as well as the transition from                                                                          columns that extend continuously between the
              the London clay also contain water-bearing                              short-term undrained soil pressures to the long-                                                                      lowest basement level and roof.
              sand layers which had the potential to cause                            term drained condition.                                                                                                 The most noteworthy transfer structures are
              construction diffi  culties.                                                                                                                                                                    located at ground level over the ballroom and
                                                  stiff  London clay. However, it was established                                                                                                            cinema, supporting the entire northern half
              Structural design                   that the foundation piles should remain in the                                                                                                            of the building superstructure. As the largest
              A cross-section of the building is shown in   London clay and not enter the Lambeth group.   Box 2. Overview of                                                                               column-free spaces in the hotel, these two
              Figure 5, with overviews of the basement   Piling into the Lambeth group would have   superstructure design                                                                                   zones were stacked one above the other to
              design and superstructure presented in   required a bentonite slurry to support the pile                                                                                                      minimise the need for further transfer structures
              Boxes 1 and 2.                      bores due to the water-bearing sands. This   |  260mm thick reinforced concrete  oor                                                                    within the basement.
                                                  would have required a signi cant amount of   slabs.                                 From this, more re ned individual FE models   wall was required. The prop slabs are formed   The ballroom  oor, over the cinema, utilised
              Basement maximisation               plant, for which there was no space on the   |  Blade columns on a typical 6.5m × 6.5m   of each prop slab were assessed. These models   integral to the liner wall with reinforcement tying   a series of concrete band beams to achieve
              With so many uses to squeeze into this   constrained site.                 grid.                                       included both the vertical and lateral loads with   them together and connecting back to the piled   the spans required. Above the ballroom, large
              constrained site, one of the  rst engineering   As such, the basement depth was typically   |  Two primary reinforced concrete cores   envelope cases of the diff erent load combinations   wall behind. This allows the safe transfer of the   transfer structures were needed to support
              activities undertaken was to understand the   limited to 31.2m, with local increases to 34.5m   and three secondary reinforced concrete   considered to  nd the most onerous design   lateral earth pressures across the basement to   the superstructure columns. A series of steel
              maximum feasible extents of the basement,   below lift pits and drainage tanks. Typically raft   cores, formed from 300mm thick   case. The RCSlab design layer in GSA was used   the basement walls (Figure 7).  trusses was chosen to provide this transfer,
              both on plan and in depth.          piles were 18m long and perimeter piles 36m,   twinwall from level 2 upwards; traditional   to generate the reinforcement required.  For non-prop slabs, the edge detail was   allowing for integration of the signi cant number
                Early in the project, it was identi ed that there   keeping them within the clay.  construction below.                Only four of the six basement slabs were used   required to avoid attracting lateral forces while   of ventilation ducts and services to the ballroom.
              was potential to extend the basement footprint                           |  Three local reinforced concrete transfer   as full prop slabs. To the north of the building are   maintaining a vertical support to the slab. This   With spans of 21m and structural depth limited
              to halfway across and below the surrounding   Foundations                  slabs ranging from 1100mm thick to          the ballroom and Odeon cinema, both double-  was achieved by casting a corbel into the liner   to 2.85m, the trusses were fabricated from large
              streets on three sides of the site, such that the   The lowest level of the building comprises a   1250mm thick.       height spaces stacked on top of each either. This   wall; the non-prop slab was then cast onto   HISTAR 460 steel sections. This design allowed
              building was larger below ground than above.   reinforced concrete piled-raft foundation slab.   |  Nine transfer beams and 24 twinwall   meant that the slabs at the  rst (B1) and third (B3)   the corbel with elastomeric strip bearings. A   the headroom in the ballroom to be maximised,
              To achieve this, a signi cant number of service   The 1500mm thick slab is designed to support:  transfer walls hidden within the   basement levels only cover half the basement.   movement joint between the slab edge and the   which was a key requirement for the client.
              diversions were required, which took over 18   |  uplift pressures (heave) due to the excavation   partitions between bedrooms, to   For B1 it was decided that this slab would not   liner wall was formed to allow the basement   Due to the earth pressures, the head of
              months to plan and complete.          equating to approx. 200kN/m  unfactored  accommodate changing column             be used as a prop slab. B3, on the other hand,   wall to de ect under the earth pressures without   the basement wall also needed propping at
                                                                        2
                In addition to maximising space on plan,   |  large column loads, transferring load where   positions as the facade steps.  is designed as a partial prop slab to the south,   making contact and to avoid loading the non-  this location. This couldn’t be achieved by the
              the maximum feasible depth was explored.   more than one pile is required for support  |  13m × 13m central atrium with three   with the remaining slab in the northeast corner   prop slab (Figure 8).  ground- oor slab due to a mismatch in levels
              The ground conditions (Figure 6) played a   |  stability loads beneath the cores  platform levels of cruciform steel   designed not to prop the basement.                                    caused by the sloping site. The initial proposal
              signi cant part in limiting the basement depth.   |  lateral propping forces.  structure and retractable fabric roof   This variation in slabs that are propping and   Basement walls       was to use the trusses to prop the head of the
              The site was generally good for excavation, with                           over.                                       non-propping meant that careful consideration   The basement walls consisted of secant piled   wall. However,  xing the ends of the trusses
              only 5m of sands and gravels overlaying the   In order to prevent further thickening of the                            of the connection details to the basement   wall to 8m depth to provide water cut-off  in the   in position would have generated large axial


                                                                  29                                                                                                                    30
           54    건 축 구 조    2022 _ 07 _ 08   제29권 / 제04호  thestructuralengineer.org  |  July 2022                                                                              July 2022  |  thestructuralengineer.org


         Londoner Hotel_TSE July 2022_The Structural Engineer.indd   29                                            22/06/2022   17:56  Londoner Hotel_TSE July 2022_The Structural Engineer.indd   30                                     22/06/2022   17:56
   51   52   53   54   55   56   57   58   59   60   61