The Londoner hotel   Project focus            Project focus   The Londoner hotel

                해외작품소개

              forces in them under vertical loads, even when   load. The two cases are considered separately   Six trusses were utilised in total, each   FIGURE 11: Aerial view of basement excavation    spoil every day. The removal of earth was an
              considering a balanced arrangement such that   as per the Building Regulations. The upward   weighing over 60t.                                                                               amazingly effi cient operation, with an 18t lorry

              the support node was at the neutral axis. This   vertical load case was demonstrated to not                                                                                                   leaving site every four minutes.
              issue was resolved by releasing the trusses   exceed the vertical load from the building above   Construction methodology                                                                       Technology played a huge part in enabling
              laterally at one end on directional bearings   and therefore does not govern the design.   Top-down versus bottom-up                                                                          McGee to carry out this exercise so effi  ciently:
              (Figure 9), with propping provided by additional   For the horizontal case, it was shown that the   When constructing a deep basement, there are                                              |  A bespoke vehicle inspection app was

              steels that can be seen adjacent to the truss in   truss members had suffi cient capacity, but this   two primary construction methods: top-down                                                  developed to ensure the  eet of lorries was
              Figure 10.                          scenario also applied a horizontal load into   and bottom-up. The construction method and                                                                   fully operational.
                The building was classed as Consequence   the truss support bearings, which had to be   sequence are fundamental to the design of the                                                       |  The Locatu manager  was used to optimise
                                                                                                                                                                                                                             2
              Class 2b as per Building Regulations Approved   designed to resist this force.  basement and must be considered upfront.                                                                        the routing of vehicles, in combination with
              Document A. However, the trusses are   In addition to the horizontal forces from   Top-down construction involves installing                                                                    cameras located around the site to  ag any
              considered to be key elements and are capable   a blast load case, the bearings had to be   piles and plunge columns from ground level to                                                       potential vehicles blocking the route, allowing
              of sustaining an accidental design loading   designed to accommodate the maximum range   basement-formation level, before casting the                                                           issues to be resolved quickly and minimise
              of 34kN/m  applied to the member and any   of movement, along the axis of the trusses, that   ground- oor slab. The ground- oor slab is then                                                  congestion around the site.
                      2
              attached components. This design load is   could be experienced in a  re scenario due to   undermined, excavating to the next basement                                                       |  Weight loading indicators on the vehicles
              assumed to act simultaneously with the other   thermal expansion. This movement is on top   slab level, and the  rst basement level is cast.                                                   highlighted when the maximum 18t limit was
              design loads on the building, but using an   of the horizontal de ection experienced due to   The process of excavation and construction of                                                    reached.
              accidental design combination of actions.  movement of the retaining wall. As such, the    oors slabs is repeated until formation level is                                                   |  A bespoke mobile dashboard was developed
                In the case of a blast above the ballroom, this   bearings allow for 280mm of positive movement   reached.                                                                                    to allow everyone in the site team to see
              applies a downward pressure in addition to the   and up to 60mm of negative contraction.   One of the major advantages of top-down                                                              information regarding progress.
              vertical load of the building above the trusses.   The bearings, weighing nearly 3t each, and   construction is that work on the superstructure
              This was shown to not exceed the ULS design   the supporting capping beam and reinforced   can occur simultaneously to construction of                                                          In total, over 8000 lorryloads of earth were
              case for the trusses and did not govern the   concrete corbels at either end were designed   the basement, providing scope for programme                                                      removed from site during the excavation. A
              design.                             to carry the loads of the trusses at the most   savings. This method also negates the need for                                                            long-reach hydraulic excavator was developed
                A blast within the ballroom could generate   onerous position. The bearings were also   a temporary propping system, as permanent                                                           speci cally for the project. Whereas projects
              both a horizontal and vertical upward blast   designed for maintenance and replacement.  prop slabs are installed as the dig progresses,                                                      traditionally have a topping-out ceremony when
                                                                                      also helping to minimise ground movements.                                                                            the tallest point of the structure is reached, we
                                                                                       However, these bene ts usually come at                                                                              celebrated with a bottoming-out ceremony, with
              FIGURE 9: Articulation of steel truss                                  an increased cost of construction. Another                                                                            news crews present and a time capsule buried
                                                                                      drawback of this method is that the vertical                                                                          35m below the ground.
                                                                                      tolerance of plunge columns can lead to          loading could have been supported on the   concrete encasement required in the permanent
                                                                                      large column areas on the lower  oors of the    plunge columns. This would have limited   case, meant the columns would have needed to   Piling
                                                                                      basement.                                        the  nishes and  t-out that could have been   be larger than with a bottom-up arrangement,   Once the formation level of the basement
                                                                                       Bottom-up construction, on the other hand,      achieved on the superstructure  oors before   even if high-strength steel was used, taking up   was reached, the process of constructing the
                                                                                      involves a phased sequence of excavation         this milestone.                   valuable space within the basement.  building could begin with piling for the raft slab.
                                                                                      and installation of temporary props as the dig                                      These considerations led to the decision to   This presented its own challenges.
                                                                                      progresses to the full basement depth. This      These two constraints limited the programme   adopt a bottom-up construction approach.  A piling rig was lowered into the excavation.
                                                                                      allows access to construct the foundations     advantages that can typically be achieved with                         Due to the temporary steel props restraining the
                                                                                      before installing permanent prop slabs, working   top-down construction. In addition, tolerances   Basement excavation  basement walls (Figure 11), height and access
                                                                                      from the bottom up. It also allows the dig to   on the plunge column verticality, estimated   In order to create the basement, 75 000m   3  to the corners of the basement was limited.
                                                                                      progress faster than in the top-down method;   to be in the order of ±100mm at the base of   of London clay was excavated prior to   To ensure the piles in these locations could be
                                                                                      however, work on the superstructure cannot     the excavation, together with the reinforced   construction, with up to 150 lorries removing   installed, the pile cages were delivered to site in
                                                                                      start until after the basement dig is complete.                                                                       sections which could be joined over the bore.
                                                                                      The positioning of the temporary props also                                                                             A smaller piling rig was utilised that could
                FIGURE 10:                                                           needs to be carefully coordinated to ensure the                                                                       operate under the temporary props, and the pile
                Installation of
                steel truss                                                           basement can be constructed around them.                                                                              locations had been carefully coordinated so that
                                                                                       The choice between bottom-up and                                                                                     cages could be threaded between the props.
                                                                                      top-down basement construction was not a
                                                                                      straightforward decision on this project. Initially,                                                                  Truss fabrication and installation
                                                                                      the contractors, who the design team engaged                                                                          The transfer trusses were formed from UC
                                                                                      with, preferred a top-down approach. However,                                                                         sections up to the maximum 356 × 406 × 1299

                                                                                      later assessment found this option to be less                                                                         UC. It would have been diffi cult to splice the
                                                                                      favourable for two main reasons:                                                                                      trusses together on site with a bolted solution.
                                                                                      1)  Multiple transfer structures within the building                                                                  Welding sections would have also been a
                                                                                        mean that load is concentrated in a handful                                                                         diffi cult and lengthy site operation. The trusses

                                                                                        of the columns in the basement. For a top-                                                                          were therefore fabricated off  site with full-
                                                                                        down approach, the team explored using                                                                              penetration butt welds (FPBWs) formed at the
                                                                                        2.4m diameter piles under these heavily                                                                             connections (Figure 12).
                                                                                        loaded columns. However, these piles were                                                                             It is critical that welding steel of this type
                                                                                        unable to support the large loads, meaning                                                                          (HISTAR 460) and thickness (up to 140mm
                                                                                        additional temporary plunge columns would                                                                           thick) is carefully considered and managed, with
                                                                                        have been needed to support the transfer                                                                            speci c welding procedures developed.
                                                                                        structures at intermediate points before the                                                                          Initially, there were some concerns about
                                                                                        raft slab was cast. Furthermore, the piles                                                                          the weldability of HISTAR steel due to pre-
                                                                                        would have penetrated the Lambeth group                                                                             existing data, in particular results of low fracture
                                                                                        and Thanet sands, requiring bentonite plant    FIGURE 12:                                                          toughness in the fusion line and heat-aff ected
                                                                                        to stabilise them during construction.         Truss weld –                                                         zone of the weld area.

                                                                                      2)  Before the raft slab was cast and plunge     through ange of                                                       As a result, the fabricator, Allerton Steel,
                                                                                                                                       chord member
                                                                                        columns encased in concrete, only temporary                                                                         produced pre-welding procedure speci cations
                                                                  31                                                                                                                    32
           56    건 축 구 조    2022 _ 07 _ 08   제29권 / 제04호  thestructuralengineer.org  |  July 2022                                                                              July 2022  |  thestructuralengineer.org


         Londoner Hotel_TSE July 2022_The Structural Engineer.indd   31                                            22/06/2022   17:56  Londoner Hotel_TSE July 2022_The Structural Engineer.indd   32                                     22/06/2022   17:57