Page 57 - 건축구조 Vol. 29 / No. 04
P. 57

The Londoner hotel   Project focus  Project focus   The Londoner hotel

                                                                                Digging deep: design and construction of The Londoner hotel

 FIGURE 5: Diagrammatic cross-section of building  slab, a drainage layer was provided to stop   FIGURE 7: Prop slab load path  river terrace deposits, with contiguous piles
 Box 1. Overview of basement   high water pressures developing beneath the     for the remaining depth. The male piles were
 design  slab. A decision was made not to provide                              1180mm diameter and spanned between the
 a heave void, as this would have increased                                    prop slabs resisting the earth pressures. In front
 |  Pile wall to basement perimeter: secant   ground movements around the excavation. The   of this sits a nominal 425mm thick reinforced
 to 8m depth to provide water cut-off in   foundations were therefore designed to resist   concrete liner wall designed to resist hydrostatic

 river terrace deposits, with contiguous   the large heave pressures.          pressures.
 piles for the remaining depth; male piles   In principle, a raft alone could have provided   Tolerance on the piles was a key issue, as

 1180mm diameter.  suffi cient foundation capacity, but the uneven               any lack of verticality had the potential to eat
 |  Nominal 425mm thick reinforced   distribution of load meant that piles were   into the 425mm liner wall and reduce the size
 concrete liner wall, doweled to pile wall   needed to control movements and deal with   of the basement. For a basement of this depth,
 to resist lateral earth and hydrostatic   areas of uplift due to heave. A piled raft analysis   this was fundamental, e.g. a 1:100 verticality
 pressures.  was carried out, modelling the relative stiff ness                 tolerance could result in an approx. 600mm
 |  Capping beam to top of pile wall,   of the soil and piles and various loading   reduction in basement size. To control tolerance,
 varying in depth from 1.6m to 3.1m to   scenarios.                            a guide wall was used and the piles were cased
 suit change in level across site.  Heave pressures increase over time, so the   for the  rst 15m. An allowable tolerance of
 |  1500mm thick piled raft to bottom of   maximum settlement and pile loads occur when   1:200 was speci ed for the cased section and
 basement, with local pits for lifts and   the building is  rst complete, in combination   1:75 for the uncased. The speci ed tolerances
 drainage tanks. Raft and piles were   with a full suite of imposed loads. However,   were generally met across the site.
 designed to resist heave pressures but   when the maximum heave pressure is applied in   A reinforced concrete capping beam is
 not hydrostatic pressure, as underside   combination with minimum vertical loads, piles   provided around the head of the piled wall
 was drained.  can go into tension with upwards de ection                     along the perimeter of the site. The capping
 |  Four levels of 350mm thick reinforced   exhibited. These are at a maximum to the north   beam is stepped in three locations to suit the
 concrete prop slabs, plus one partial   FIGURE 6: Cross-section through building showing   of the site where columns are carrying a lower   FIGURE 8: Non-prop slab connection details  changing ground levels and the geometry of the

 prop slab, to transfer lateral earth   different ground conditions  axial load due to transfer structures at the upper   connection to ground- oor slabs and transfer
 pressures across basement void.  levels.                                      trusses.
 |  Six S460 HISTAR transfer trusses,
 spanning up to 21m and weighing over   Prop slabs                             Transfer structures
 60t each.  As well as supporting vertical loads, the basement                 On the bedroom  oors, columns were provided
 |  Four levels of temporary steel props,    oor slabs resist signi cant lateral earth pressures.   at regular centres hidden within partition walls,
 specially fabricated for the project.  A coarse 3D  nite element (FE) model of the   allowing shallow reinforced concrete  oor slabs
 basement with each of the prop slabs was created                              to be used. However, below the bedroom levels,
 in Oasys GSA  to understand how the lateral                                   several column-free spaces were required to
 1
 Groundwater observations indicated water to   loads were transferred between levels through   allow for open-plan function and reception
 have been encountered at between 4m and 6m   the basement perimeter walls and stability   spaces. The arrangement led to various transfer
 depth. This suggested a potential for a shallow   cores. The model was staged to capture the   structures throughout the building, the majority
 aquifer to be present within the river terrace   behaviour of the basement as each  oor was   of which are located at ground and  rst  oor.
 gravel perched on top of the London clay. The   installed and the subsequent temporary props   Incredibly, the building contains only two
 Lambeth group and Thanet sands beneath   were removed, as well as the transition from   columns that extend continuously between the
 the London clay also contain water-bearing   short-term undrained soil pressures to the long-  lowest basement level and roof.
 sand layers which had the potential to cause   term drained condition.          The most noteworthy transfer structures are
 construction diffi  culties.                                                    located at ground level over the ballroom and
 stiff  London clay. However, it was established                                cinema, supporting the entire northern half
 Structural design  that the foundation piles should remain in the             of the building superstructure. As the largest
 A cross-section of the building is shown in   London clay and not enter the Lambeth group.   Box 2. Overview of   column-free spaces in the hotel, these two
 Figure 5, with overviews of the basement   Piling into the Lambeth group would have   superstructure design  zones were stacked one above the other to
 design and superstructure presented in   required a bentonite slurry to support the pile   minimise the need for further transfer structures
 Boxes 1 and 2.  bores due to the water-bearing sands. This   |  260mm thick reinforced concrete  oor   within the basement.
 would have required a signi cant amount of   slabs.  From this, more re ned individual FE models   wall was required. The prop slabs are formed   The ballroom  oor, over the cinema, utilised
 Basement maximisation  plant, for which there was no space on the   |  Blade columns on a typical 6.5m × 6.5m   of each prop slab were assessed. These models   integral to the liner wall with reinforcement tying   a series of concrete band beams to achieve
 With so many uses to squeeze into this   constrained site.  grid.  included both the vertical and lateral loads with   them together and connecting back to the piled   the spans required. Above the ballroom, large
 constrained site, one of the  rst engineering   As such, the basement depth was typically   |  Two primary reinforced concrete cores   envelope cases of the diff erent load combinations   wall behind. This allows the safe transfer of the   transfer structures were needed to support
 activities undertaken was to understand the   limited to 31.2m, with local increases to 34.5m   and three secondary reinforced concrete   considered to  nd the most onerous design   lateral earth pressures across the basement to   the superstructure columns. A series of steel
 maximum feasible extents of the basement,   below lift pits and drainage tanks. Typically raft   cores, formed from 300mm thick   case. The RCSlab design layer in GSA was used   the basement walls (Figure 7).  trusses was chosen to provide this transfer,
 both on plan and in depth.  piles were 18m long and perimeter piles 36m,   twinwall from level 2 upwards; traditional   to generate the reinforcement required.  For non-prop slabs, the edge detail was   allowing for integration of the signi cant number
 Early in the project, it was identi ed that there   keeping them within the clay.  construction below.  Only four of the six basement slabs were used   required to avoid attracting lateral forces while   of ventilation ducts and services to the ballroom.
 was potential to extend the basement footprint   |  Three local reinforced concrete transfer   as full prop slabs. To the north of the building are   maintaining a vertical support to the slab. This   With spans of 21m and structural depth limited
 to halfway across and below the surrounding   Foundations  slabs ranging from 1100mm thick to   the ballroom and Odeon cinema, both double-  was achieved by casting a corbel into the liner   to 2.85m, the trusses were fabricated from large
 streets on three sides of the site, such that the   The lowest level of the building comprises a   1250mm thick.  height spaces stacked on top of each either. This   wall; the non-prop slab was then cast onto   HISTAR 460 steel sections. This design allowed
 building was larger below ground than above.   reinforced concrete piled-raft foundation slab.   |  Nine transfer beams and 24 twinwall   meant that the slabs at the  rst (B1) and third (B3)   the corbel with elastomeric strip bearings. A   the headroom in the ballroom to be maximised,
 To achieve this, a signi cant number of service   The 1500mm thick slab is designed to support:  transfer walls hidden within the   basement levels only cover half the basement.   movement joint between the slab edge and the   which was a key requirement for the client.
 diversions were required, which took over 18   |  uplift pressures (heave) due to the excavation   partitions between bedrooms, to   For B1 it was decided that this slab would not   liner wall was formed to allow the basement   Due to the earth pressures, the head of
 months to plan and complete.  equating to approx. 200kN/m  unfactored  accommodate changing column   be used as a prop slab. B3, on the other hand,   wall to de ect under the earth pressures without   the basement wall also needed propping at
 2
 In addition to maximising space on plan,   |  large column loads, transferring load where   positions as the facade steps.  is designed as a partial prop slab to the south,   making contact and to avoid loading the non-  this location. This couldn’t be achieved by the
 the maximum feasible depth was explored.   more than one pile is required for support  |  13m × 13m central atrium with three   with the remaining slab in the northeast corner   prop slab (Figure 8).  ground- oor slab due to a mismatch in levels
 The ground conditions (Figure 6) played a   |  stability loads beneath the cores  platform levels of cruciform steel   designed not to prop the basement.  caused by the sloping site. The initial proposal
 signi cant part in limiting the basement depth.   |  lateral propping forces.  structure and retractable fabric roof   This variation in slabs that are propping and   Basement walls  was to use the trusses to prop the head of the
 The site was generally good for excavation, with   over.  non-propping meant that careful consideration   The basement walls consisted of secant piled   wall. However,  xing the ends of the trusses
 only 5m of sands and gravels overlaying the   In order to prevent further thickening of the   of the connection details to the basement   wall to 8m depth to provide water cut-off  in the   in position would have generated large axial


 29                                                         30
 thestructuralengineer.org  |  July 2022          July 2022  |  thestructuralengineer.org  Journal of  The Korea  Structural  Engineers Association  55
                                                                한국건축구조기술사회지

 Londoner Hotel_TSE July 2022_The Structural Engineer.indd   29  22/06/2022   17:56  Londoner Hotel_TSE July 2022_The Structural Engineer.indd   30  22/06/2022   17:56
   52   53   54   55   56   57   58   59   60   61   62